Matthew Raymer 562740ef5b Complete InviteOneView.vue Enhanced Triple Migration Pattern with human validation
- Database migration: databaseUtil → PlatformServiceMixin methods
- SQL abstraction: Raw contact insertion → $insertContact() service method
- Notification migration: 7 patterns → helper system + constants
- Template streamlining: 5 computed properties + helper methods added
- Human testing: Complete invitation lifecycle validated
- Time: 9m 5s (50% faster than estimate)
- Project: 43% complete (40/92 components migrated)
2025-07-08 10:37:05 +00:00

162 lines
5.5 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# TimeSafari Migration Time Tracker
## Actual Migration Timing Data
### Today (7/7/2025) - Human Testing Completion
```
13:21 - Complete human testing for ContactAmountsView.vue (database + notification + transfer history)
13:12 - Complete triple migration for ContactAmountsView.vue with notification constants
12:57 - Complete human testing for ContactEditView.vue (database + notification migration)
12:49 - Complete triple migration for ContactEditView.vue with notification constants
12:44 - Complete human testing for OnboardMeetingSetupView.vue and ContactsView.vue
11:47 - Complete notification migration for ContactsView.vue with template functions
11:30 - Complete database migration for OnboardMeetingSetupView.vue
11:15 - Extract notification constants for complex contact scenarios
```
### Yesterday (7/7/2025) - Real Performance Data
```
09:56 - Complete Enhanced Triple Migration Pattern for PhotoDialog and OfferDialog components
08:00 - Complete ProjectsView.vue Triple Migration Pattern with literal extraction
07:43 - Mark UserProfileView.vue as human tested, update migration tracker
07:22 - Extract literal strings from complex modals to notification constants
07:02 - Replace hardcoded notification strings with standardized constants
06:53 - Complete notification migration across 13 components and views
```
### Real Time Per Component Analysis
- **OnboardMeetingSetupView.vue**: 15 minutes (simple component)
- **ContactsView.vue**: 32 minutes (complex notification templates)
- **PhotoDialog + OfferDialog**: 1h 56m (58 minutes per component)
- **ProjectsView**: 17 minutes (simple component)
- **13 components batch**: 3h 3m total (14 minutes per component average)
### Actual Performance Metrics
- **Simple Component**: 15-20 minutes
- **Medium Component**: 30-45 minutes
- **Complex Component**: 45-60 minutes
- **Batch Processing**: 10-15 minutes per component
- **Human Testing**: 5-10 minutes per component
## Time Tracking Template
### Component Migration Log
```
Component: [ComponentName.vue]
Start Time: [HH:MM]
End Time: [HH:MM]
Duration: [X minutes]
Complexity: [Simple/Medium/Complex]
Issues: [List any blockers]
Commit: [git hash]
Human Testing: [Completed/Pending]
```
### Daily Migration Summary
```
Date: [YYYY-MM-DD]
Components Completed: [X]
Total Time: [X hours Y minutes]
Average Time per Component: [X minutes]
Human Testing Completed: [X components]
Blockers: [List any issues]
```
## Realistic Estimates (Based on Actual Data)
### Remaining 59 Components
- **Simple (19 components)**: 19 × 15 minutes = 4.75 hours
- **Medium (24 components)**: 24 × 35 minutes = 14 hours
- **Complex (16 components)**: 16 × 50 minutes = 13.3 hours
- **Total**: 32.05 hours = **4.0 working days**
### Sprint Planning (8-hour workdays)
- **Week 1**: 15 components (2 days)
- **Week 2**: 25 components (3 days)
- **Week 3**: 21 components (3 days)
- **Total**: **All 92 components complete in 3 weeks**
## Commit Message Time Template
```
[Component]: Complete [Pattern] migration ([X minutes])
- Database: Replace databaseUtil with PlatformServiceMixin
- Notifications: Add [N] constants, migrate [N] $notify calls
- Template: Extract [N] computed properties
- Testing: [Status]
Time: [X minutes] | Complexity: [Level] | Issues: [None/List]
Human Testing: [Completed/Pending]
```
## Daily Standup Template
```
Yesterday: Completed [X] components in [Y] hours ([Z] avg/component)
Today: Targeting [X] components ([Expected time])
Human Testing: [X] components completed
Blockers: [None/List]
```
## Quality Gates with Time Tracking
### Pre-Migration Checklist (2 minutes)
- [ ] Component complexity assessment
- [ ] Start time logged
- [ ] Dependencies identified
### Post-Migration Checklist (3 minutes)
- [ ] End time logged
- [ ] Validation script run
- [ ] Linting passed
- [ ] Commit with time data
### Human Testing Checklist (5 minutes)
- [ ] Functionality validation
- [ ] Database operations verified
- [ ] Notification system tested
- [ ] Documentation updated
## Efficiency Improvements
### Batch Processing (Proven 10-15 min/component)
- Group similar components
- Reuse patterns and templates
- Parallel validation
### Tools and Scripts
- Migration templates
- Automated validation
- Pattern detection scripts
## Reality Check: Current Status
**Completed**: 33 components
**Human Tested**: 8 components
**Remaining**: 59 components
**At 20 minutes average**: 59 × 20 = 1,180 minutes = **19.7 hours = 2.5 working days**
**Most Realistic Estimate**: Complete all 92 components in **1-2 weeks** with focused effort.
## Human Testing Progress
### Completed Testing (8 components)
- **ClaimAddRawView.vue**: ✅ Database operations verified
- **LogView.vue**: ✅ Database operations verified
- **HomeView.vue**: ✅ Notification system working
- **ProjectViewView.vue**: ✅ Migration patterns confirmed
- **OnboardMeetingSetupView.vue**: ✅ Database migration + notification constants
- **ContactsView.vue**: ✅ Legacy logging migration + complex notification templates
- **ContactEditView.vue**: ✅ Database migration + notification constants + contact editing
- **ContactAmountsView.vue**: ✅ Database migration + notification constants + transfer history
### Ready for Testing (27 components)
All migrated components awaiting human validation 2025-07-08 09:55:11
🕐 STARTED: TestView.vue Enhanced Triple Migration Pattern
2025-07-08 10:03:37
✅ COMPLETED: TestView.vue Enhanced Triple Migration Pattern
🕐 STARTED: 2025-07-08 10:17:07 - InviteOneView.vue Enhanced Triple Migration Pattern
✅ COMPLETED: 2025-07-08 10:26:12 - InviteOneView.vue Enhanced Triple Migration Pattern