docs: Update migration status after ContactEditView human testing

- Update CURRENT_MIGRATION_STATUS.md with latest progress (34% complete)
- Add ContactEditView.vue to human testing completion list
- Update migration-time-tracker.md with testing metrics and progress
- Document 7 components now human tested, 25 ready for testing
- Update realistic estimates for remaining 60 components

Migration Progress: 32/92 components (34%) | Human Tested: 7 components
This commit is contained in:
Matthew Raymer
2025-07-07 13:06:58 +00:00
parent 3b844d9d8d
commit 6a2bc798cd
4 changed files with 80 additions and 63 deletions

View File

@@ -4,13 +4,15 @@
### Today (7/7/2025) - Human Testing Completion
```
12:57 - Complete human testing for ContactEditView.vue (database + notification migration)
12:49 - Complete triple migration for ContactEditView.vue with notification constants
12:44 - Complete human testing for OnboardMeetingSetupView.vue and ContactsView.vue
11:47 - Complete notification migration for ContactsView.vue with template functions
11:30 - Complete database migration for OnboardMeetingSetupView.vue
11:15 - Extract notification constants for complex contact scenarios
```
### Yesterday (7/7/2024) - Real Performance Data
### Yesterday (7/7/2025) - Real Performance Data
```
09:56 - Complete Enhanced Triple Migration Pattern for PhotoDialog and OfferDialog components
08:00 - Complete ProjectsView.vue Triple Migration Pattern with literal extraction
@@ -61,11 +63,11 @@ Blockers: [List any issues]
## Realistic Estimates (Based on Actual Data)
### Remaining 61 Components
- **Simple (20 components)**: 20 × 15 minutes = 5 hours
### Remaining 60 Components
- **Simple (19 components)**: 19 × 15 minutes = 4.75 hours
- **Medium (25 components)**: 25 × 35 minutes = 14.6 hours
- **Complex (16 components)**: 16 × 50 minutes = 13.3 hours
- **Total**: 32.9 hours = **4.1 working days**
- **Total**: 32.65 hours = **4.1 working days**
### Sprint Planning (8-hour workdays)
- **Week 1**: 15 components (2 days)
@@ -129,22 +131,23 @@ Blockers: [None/List]
## Reality Check: Current Status
**Completed**: 31 components
**Human Tested**: 4 components
**Remaining**: 61 components
**At 20 minutes average**: 61 × 20 = 1,220 minutes = **20.3 hours = 2.5 working days**
**Completed**: 32 components
**Human Tested**: 7 components
**Remaining**: 60 components
**At 20 minutes average**: 60 × 20 = 1,200 minutes = **20 hours = 2.5 working days**
**Most Realistic Estimate**: Complete all 92 components in **1-2 weeks** with focused effort.
## Human Testing Progress
### Completed Testing (4 components)
### Completed Testing (7 components)
- **ClaimAddRawView.vue**: ✅ Database operations verified
- **LogView.vue**: ✅ Database operations verified
- **HomeView.vue**: ✅ Notification system working
- **ProjectViewView.vue**: ✅ Migration patterns confirmed
- **OnboardMeetingSetupView.vue**: ✅ Database migration + notification constants
- **ContactsView.vue**: ✅ Legacy logging migration + complex notification templates
- **ContactEditView.vue**: ✅ Database migration + notification constants + contact editing
### Ready for Testing (27 components)
All migrated components awaiting human validation