docs: Update migration status after ContactEditView human testing
- Update CURRENT_MIGRATION_STATUS.md with latest progress (34% complete) - Add ContactEditView.vue to human testing completion list - Update migration-time-tracker.md with testing metrics and progress - Document 7 components now human tested, 25 ready for testing - Update realistic estimates for remaining 60 components Migration Progress: 32/92 components (34%) | Human Tested: 7 components
This commit is contained in:
@@ -4,13 +4,15 @@
|
||||
|
||||
### Today (7/7/2025) - Human Testing Completion
|
||||
```
|
||||
12:57 - Complete human testing for ContactEditView.vue (database + notification migration)
|
||||
12:49 - Complete triple migration for ContactEditView.vue with notification constants
|
||||
12:44 - Complete human testing for OnboardMeetingSetupView.vue and ContactsView.vue
|
||||
11:47 - Complete notification migration for ContactsView.vue with template functions
|
||||
11:30 - Complete database migration for OnboardMeetingSetupView.vue
|
||||
11:15 - Extract notification constants for complex contact scenarios
|
||||
```
|
||||
|
||||
### Yesterday (7/7/2024) - Real Performance Data
|
||||
### Yesterday (7/7/2025) - Real Performance Data
|
||||
```
|
||||
09:56 - Complete Enhanced Triple Migration Pattern for PhotoDialog and OfferDialog components
|
||||
08:00 - Complete ProjectsView.vue Triple Migration Pattern with literal extraction
|
||||
@@ -61,11 +63,11 @@ Blockers: [List any issues]
|
||||
|
||||
## Realistic Estimates (Based on Actual Data)
|
||||
|
||||
### Remaining 61 Components
|
||||
- **Simple (20 components)**: 20 × 15 minutes = 5 hours
|
||||
### Remaining 60 Components
|
||||
- **Simple (19 components)**: 19 × 15 minutes = 4.75 hours
|
||||
- **Medium (25 components)**: 25 × 35 minutes = 14.6 hours
|
||||
- **Complex (16 components)**: 16 × 50 minutes = 13.3 hours
|
||||
- **Total**: 32.9 hours = **4.1 working days**
|
||||
- **Total**: 32.65 hours = **4.1 working days**
|
||||
|
||||
### Sprint Planning (8-hour workdays)
|
||||
- **Week 1**: 15 components (2 days)
|
||||
@@ -129,22 +131,23 @@ Blockers: [None/List]
|
||||
|
||||
## Reality Check: Current Status
|
||||
|
||||
**Completed**: 31 components
|
||||
**Human Tested**: 4 components
|
||||
**Remaining**: 61 components
|
||||
**At 20 minutes average**: 61 × 20 = 1,220 minutes = **20.3 hours = 2.5 working days**
|
||||
**Completed**: 32 components
|
||||
**Human Tested**: 7 components
|
||||
**Remaining**: 60 components
|
||||
**At 20 minutes average**: 60 × 20 = 1,200 minutes = **20 hours = 2.5 working days**
|
||||
|
||||
**Most Realistic Estimate**: Complete all 92 components in **1-2 weeks** with focused effort.
|
||||
|
||||
## Human Testing Progress
|
||||
|
||||
### Completed Testing (4 components)
|
||||
### Completed Testing (7 components)
|
||||
- **ClaimAddRawView.vue**: ✅ Database operations verified
|
||||
- **LogView.vue**: ✅ Database operations verified
|
||||
- **HomeView.vue**: ✅ Notification system working
|
||||
- **ProjectViewView.vue**: ✅ Migration patterns confirmed
|
||||
- **OnboardMeetingSetupView.vue**: ✅ Database migration + notification constants
|
||||
- **ContactsView.vue**: ✅ Legacy logging migration + complex notification templates
|
||||
- **ContactEditView.vue**: ✅ Database migration + notification constants + contact editing
|
||||
|
||||
### Ready for Testing (27 components)
|
||||
All migrated components awaiting human validation
|
||||