You can not select more than 25 topics
Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
4.7 KiB
4.7 KiB
TimeSafari Migration Time Tracker
Actual Migration Timing Data
Today (7/7/2025) - Human Testing Completion
12:44 - Complete human testing for OnboardMeetingSetupView.vue and ContactsView.vue
11:47 - Complete notification migration for ContactsView.vue with template functions
11:30 - Complete database migration for OnboardMeetingSetupView.vue
11:15 - Extract notification constants for complex contact scenarios
Yesterday (7/7/2024) - Real Performance Data
09:56 - Complete Enhanced Triple Migration Pattern for PhotoDialog and OfferDialog components
08:00 - Complete ProjectsView.vue Triple Migration Pattern with literal extraction
07:43 - Mark UserProfileView.vue as human tested, update migration tracker
07:22 - Extract literal strings from complex modals to notification constants
07:02 - Replace hardcoded notification strings with standardized constants
06:53 - Complete notification migration across 13 components and views
Real Time Per Component Analysis
- OnboardMeetingSetupView.vue: 15 minutes (simple component)
- ContactsView.vue: 32 minutes (complex notification templates)
- PhotoDialog + OfferDialog: 1h 56m (58 minutes per component)
- ProjectsView: 17 minutes (simple component)
- 13 components batch: 3h 3m total (14 minutes per component average)
Actual Performance Metrics
- Simple Component: 15-20 minutes
- Medium Component: 30-45 minutes
- Complex Component: 45-60 minutes
- Batch Processing: 10-15 minutes per component
- Human Testing: 5-10 minutes per component
Time Tracking Template
Component Migration Log
Component: [ComponentName.vue]
Start Time: [HH:MM]
End Time: [HH:MM]
Duration: [X minutes]
Complexity: [Simple/Medium/Complex]
Issues: [List any blockers]
Commit: [git hash]
Human Testing: [Completed/Pending]
Daily Migration Summary
Date: [YYYY-MM-DD]
Components Completed: [X]
Total Time: [X hours Y minutes]
Average Time per Component: [X minutes]
Human Testing Completed: [X components]
Blockers: [List any issues]
Realistic Estimates (Based on Actual Data)
Remaining 61 Components
- Simple (20 components): 20 × 15 minutes = 5 hours
- Medium (25 components): 25 × 35 minutes = 14.6 hours
- Complex (16 components): 16 × 50 minutes = 13.3 hours
- Total: 32.9 hours = 4.1 working days
Sprint Planning (8-hour workdays)
- Week 1: 15 components (2 days)
- Week 2: 25 components (3 days)
- Week 3: 21 components (3 days)
- Total: All 92 components complete in 3 weeks
Commit Message Time Template
[Component]: Complete [Pattern] migration ([X minutes])
- Database: Replace databaseUtil with PlatformServiceMixin
- Notifications: Add [N] constants, migrate [N] $notify calls
- Template: Extract [N] computed properties
- Testing: [Status]
Time: [X minutes] | Complexity: [Level] | Issues: [None/List]
Human Testing: [Completed/Pending]
Daily Standup Template
Yesterday: Completed [X] components in [Y] hours ([Z] avg/component)
Today: Targeting [X] components ([Expected time])
Human Testing: [X] components completed
Blockers: [None/List]
Quality Gates with Time Tracking
Pre-Migration Checklist (2 minutes)
- Component complexity assessment
- Start time logged
- Dependencies identified
Post-Migration Checklist (3 minutes)
- End time logged
- Validation script run
- Linting passed
- Commit with time data
Human Testing Checklist (5 minutes)
- Functionality validation
- Database operations verified
- Notification system tested
- Documentation updated
Efficiency Improvements
Batch Processing (Proven 10-15 min/component)
- Group similar components
- Reuse patterns and templates
- Parallel validation
Tools and Scripts
- Migration templates
- Automated validation
- Pattern detection scripts
Reality Check: Current Status
Completed: 31 components Human Tested: 4 components Remaining: 61 components At 20 minutes average: 61 × 20 = 1,220 minutes = 20.3 hours = 2.5 working days
Most Realistic Estimate: Complete all 92 components in 1-2 weeks with focused effort.
Human Testing Progress
Completed Testing (4 components)
- ClaimAddRawView.vue: ✅ Database operations verified
- LogView.vue: ✅ Database operations verified
- HomeView.vue: ✅ Notification system working
- ProjectViewView.vue: ✅ Migration patterns confirmed
- OnboardMeetingSetupView.vue: ✅ Database migration + notification constants
- ContactsView.vue: ✅ Legacy logging migration + complex notification templates
Ready for Testing (27 components)
All migrated components awaiting human validation