TimeSafari Migration Time Tracker

Actual Migration Timing Data

Today (7/7/2025) - Human Testing Completion

12:44 - Complete human testing for OnboardMeetingSetupView.vue and ContactsView.vue
11:47 - Complete notification migration for ContactsView.vue with template functions
11:30 - Complete database migration for OnboardMeetingSetupView.vue
11:15 - Extract notification constants for complex contact scenarios

Yesterday (7/7/2024) - Real Performance Data

09:56 - Complete Enhanced Triple Migration Pattern for PhotoDialog and OfferDialog components
08:00 - Complete ProjectsView.vue Triple Migration Pattern with literal extraction
07:43 - Mark UserProfileView.vue as human tested, update migration tracker  
07:22 - Extract literal strings from complex modals to notification constants
07:02 - Replace hardcoded notification strings with standardized constants
06:53 - Complete notification migration across 13 components and views

Real Time Per Component Analysis

  • OnboardMeetingSetupView.vue: 15 minutes (simple component)
  • ContactsView.vue: 32 minutes (complex notification templates)
  • PhotoDialog + OfferDialog: 1h 56m (58 minutes per component)
  • ProjectsView: 17 minutes (simple component)
  • 13 components batch: 3h 3m total (14 minutes per component average)

Actual Performance Metrics

  • Simple Component: 15-20 minutes
  • Medium Component: 30-45 minutes
  • Complex Component: 45-60 minutes
  • Batch Processing: 10-15 minutes per component
  • Human Testing: 5-10 minutes per component

Time Tracking Template

Component Migration Log

Component: [ComponentName.vue]
Start Time: [HH:MM]
End Time: [HH:MM]
Duration: [X minutes]
Complexity: [Simple/Medium/Complex]
Issues: [List any blockers]
Commit: [git hash]
Human Testing: [Completed/Pending]

Daily Migration Summary

Date: [YYYY-MM-DD]
Components Completed: [X]
Total Time: [X hours Y minutes]
Average Time per Component: [X minutes]
Human Testing Completed: [X components]
Blockers: [List any issues]

Realistic Estimates (Based on Actual Data)

Remaining 61 Components

  • Simple (20 components): 20 × 15 minutes = 5 hours
  • Medium (25 components): 25 × 35 minutes = 14.6 hours
  • Complex (16 components): 16 × 50 minutes = 13.3 hours
  • Total: 32.9 hours = 4.1 working days

Sprint Planning (8-hour workdays)

  • Week 1: 15 components (2 days)
  • Week 2: 25 components (3 days)
  • Week 3: 21 components (3 days)
  • Total: All 92 components complete in 3 weeks

Commit Message Time Template

[Component]: Complete [Pattern] migration ([X minutes])

- Database: Replace databaseUtil with PlatformServiceMixin
- Notifications: Add [N] constants, migrate [N] $notify calls  
- Template: Extract [N] computed properties
- Testing: [Status]

Time: [X minutes] | Complexity: [Level] | Issues: [None/List]
Human Testing: [Completed/Pending]

Daily Standup Template

Yesterday: Completed [X] components in [Y] hours ([Z] avg/component)
Today: Targeting [X] components ([Expected time])
Human Testing: [X] components completed
Blockers: [None/List]

Quality Gates with Time Tracking

Pre-Migration Checklist (2 minutes)

  • Component complexity assessment
  • Start time logged
  • Dependencies identified

Post-Migration Checklist (3 minutes)

  • End time logged
  • Validation script run
  • Linting passed
  • Commit with time data

Human Testing Checklist (5 minutes)

  • Functionality validation
  • Database operations verified
  • Notification system tested
  • Documentation updated

Efficiency Improvements

Batch Processing (Proven 10-15 min/component)

  • Group similar components
  • Reuse patterns and templates
  • Parallel validation

Tools and Scripts

  • Migration templates
  • Automated validation
  • Pattern detection scripts

Reality Check: Current Status

Completed: 31 components Human Tested: 4 components Remaining: 61 components At 20 minutes average: 61 × 20 = 1,220 minutes = 20.3 hours = 2.5 working days

Most Realistic Estimate: Complete all 92 components in 1-2 weeks with focused effort.

Human Testing Progress

Completed Testing (4 components)

  • ClaimAddRawView.vue: Database operations verified
  • LogView.vue: Database operations verified
  • HomeView.vue: Notification system working
  • ProjectViewView.vue: Migration patterns confirmed
  • OnboardMeetingSetupView.vue: Database migration + notification constants
  • ContactsView.vue: Legacy logging migration + complex notification templates

Ready for Testing (27 components)

All migrated components awaiting human validation