TimeSafari Migration Time Tracker
Actual Migration Timing Data
Yesterday (7/7/2024) - Real Performance Data
09:56 - Complete Enhanced Triple Migration Pattern for PhotoDialog and OfferDialog components
08:00 - Complete ProjectsView.vue Triple Migration Pattern with literal extraction
07:43 - Mark UserProfileView.vue as human tested, update migration tracker
07:22 - Extract literal strings from complex modals to notification constants
07:02 - Replace hardcoded notification strings with standardized constants
06:53 - Complete notification migration across 13 components and views
Real Time Per Component Analysis
- PhotoDialog + OfferDialog: 1h 56m (58 minutes per component)
- ProjectsView: 17 minutes (simple component)
- 13 components batch: 3h 3m total (14 minutes per component average)
Actual Performance Metrics
- Simple Component: 15-20 minutes
- Medium Component: 30-45 minutes
- Complex Component: 45-60 minutes
- Batch Processing: 10-15 minutes per component
Time Tracking Template
Component Migration Log
Component: [ComponentName.vue]
Start Time: [HH:MM]
End Time: [HH:MM]
Duration: [X minutes]
Complexity: [Simple/Medium/Complex]
Issues: [List any blockers]
Commit: [git hash]
Daily Migration Summary
Date: [YYYY-MM-DD]
Components Completed: [X]
Total Time: [X hours Y minutes]
Average Time per Component: [X minutes]
Blockers: [List any issues]
Realistic Estimates (Based on Actual Data)
Remaining 65 Components
- Simple (25 components): 25 × 15 minutes = 6.25 hours
- Medium (25 components): 25 × 35 minutes = 14.6 hours
- Complex (15 components): 15 × 50 minutes = 12.5 hours
- Total: 33.35 hours = 4.2 working days
Sprint Planning (8-hour workdays)
- Week 1: 15 components (2 days)
- Week 2: 25 components (3 days)
- Week 3: 25 components (3 days)
- Total: All 92 components complete in 3 weeks
Commit Message Time Template
[Component]: Complete [Pattern] migration ([X minutes])
- Database: Replace databaseUtil with PlatformServiceMixin
- Notifications: Add [N] constants, migrate [N] $notify calls
- Template: Extract [N] computed properties
- Testing: [Status]
Time: [X minutes] | Complexity: [Level] | Issues: [None/List]
Daily Standup Template
Yesterday: Completed [X] components in [Y] hours ([Z] avg/component)
Today: Targeting [X] components ([Expected time])
Blockers: [None/List]
Quality Gates with Time Tracking
Pre-Migration Checklist (2 minutes)
- Component complexity assessment
- Start time logged
- Dependencies identified
Post-Migration Checklist (3 minutes)
- End time logged
- Validation script run
- Linting passed
- Commit with time data
Efficiency Improvements
Batch Processing (Proven 10-15 min/component)
- Group similar components
- Reuse patterns and templates
- Parallel validation
Tools and Scripts
- Migration templates
- Automated validation
- Pattern detection scripts
Reality Check: Current Status
Completed: 23 components Remaining: 69 components At 20 minutes average: 69 × 20 = 1,380 minutes = 23 hours = 3 working days
Most Realistic Estimate: Complete all 92 components in 1-2 weeks with focused effort.